Question: 1
The project is currently in the execution phase. During a project update meeting for the key stakeholders, they have requested that you provide them with a detailed list of the current engagement levels of the project stakeholders- As a project manager of a construction project, which of the following documents will help you for this purpose?
Question: 2
You are a Project Manager working on a project to create high-efficiency electric motors for a company introducing a new car. Half the project work has been completed. You are currently reviewing your stakeholder engagement plan. You found that some of the resisting stakeholders have now become supportive. As the Project Manager, you should now update which of the following documents first?
Question: 3
You are a project manager and you are in the closing phase. You want to report the final status of the closed contract to the stakeholders. Which form of communication is appropriate?
Question: 4
You are the Project Manager and are currently in the monitoring process group. You and your team are trying to identify the relationship between an independent variable and the dependent variable by plotting their values on a diagram. One of your team members asks you what this diagram is known as:
Question: 5
You are a Project Manager hired by a construction company, and the sponsor is developing a document which authorizes the project manager. Which is this document?