Question: 1
During a project management planning meeting two key stakeholders have conflicting interests. One requires added time to implement a new system to support the project, while the other refuses to delay the launch date due to previous time commitments.
What should the project manager do?
Question: 2
A stakeholder requests a change to the project. The project manage wants to avoid wasting the time of the change control board(CCB) and decides to approve the change themselves.
What should the project manager do to make sure they can approvers change?
Question: 3
A project manager obtains approval of an important deliverable. Later, while reviewing the monthly progress report, they notice that
that deliverable's status has been changed back to "pending." it is discovered that a new request for approval was submitted by the client team.
What should the project manager do first to avoid this problem in the future?
Question: 4
A multinational project includes stakeholders from various locations and cultures. During the final acceptance stage, a new stakeholder is added who refuses to provide final approval.
What should the project manager do?
Question: 5
During a project demonstration, a team member provides sample test data to the client without consulting the project manager. This delays the project.
What should the project manager do to avWhat should the project manager do to avoid incurring fines?oid this in the future