Question: 1
A recently appointed project manager is in constant conflict with a senior manager Since this is not ideal for the team, the project manager wants to resolve this.
What should the project manager do?
Question: 2
A product implementation project has a baseline schedule that indicates it should be complete wthin 30 days using three internal resources. As it nears completion, the Project manager learns that one resource has tell the project team. The sponsor approves hring an external resource at an additional cost.
To determine it the contingency reserve will be requited, what should the project manager calculate?
Question: 3
During an IT solution implementation project, the project manager learns that, due to security concerns, the project is no hold because the client refuse to grant access to required data. What should the project manager do next?
Question: 4
Team members on a life cycle replacement project are accustomed to frequently changing requirements even without formal approval. What should the project manager do?
Question: 5
A project team must implement a solution to replace a company's legacy system by adding new modules to newly deployed software. A Stakeholder recommends another product that has better functionality than the deployed software.
What should the project manager do to resolve this?