Question: 1
An ongoing cross-functional project has team members located in several ditTeient countries, and stakeholders who provide insufficient support. How can the project manager improve this situation?
Question: 2
A customer asks the project manager to estimate the time required to include a missing functionality. The customer thinks that three sufficient to implement this change However, the project management office (PMO) believes that seven days are required, while the technical lead feels that 10 days are needed.
What should the project manager use to estimate the time required for the change?
Question: 3
A project manager is using control charts to determine whether or not a process is stable or has predictable performance. The upper and lower control limits are determined by the customer A set of 18 data points were recorded and eight consecutive data points were found to be above the mean.
What can the project manager conclude from this finding?
Question: 4
It was found that the developers are reluctant to perform changes on a particular system because the person who developed the system has left the organization The remaining staff are not familiar with the technical details.
What should the project manager have done to avoid this situation?
Question: 5
During a project's initial phase, a new regulation is introduced. The regulation has the potential to impact the projects schedule the and budget.
What should the project manager do before beginning the planning stage?