Question: 1
A project manager is closing a project, but can only perform half of the closure activities due to the project's long-term payback period. The project manager should be responsible for which aspects of closure?
Question: 2
While reviewing the business case for a newly assigned project a project manager realizes that the project is lacking financial information to determine the overall benefit of the project for the company. What should the project manager do before starting to plan the project?
Question: 3
A project team member identifies a simple change that will improve product quality without impacting the project budget. What should the project manager do?
Question: 4
A project has a schedule performance index (SPI) of 1.2 for all project work, and an SPI of 0 8 for the critical path. How should the project manager classify this project?
Question: 5
A project manager needs stakeholder consensus and approval on high-level project requirements in order to complete the project charter. However, one key stakeholder is ignoring the project manager's requests for input.
What should the project manager do?