Question: 1
An organization is implementing changes to its financial risk management portfolio. The project manager has been assigned to a system upgrade project that is required to be completed by a specific date. The project has completed the planning phase and started the execution phase. After a period of time, the project manager identifies major difficulties related to resourcing constraints which will prevent the project from achieving the committed go-live date.
What should the project manager do?
Question: 2
A project to deliver financial and administrative changes related to taxation regulations is on schedule according to the project management plan, agreed requirements, and performance indicators. However based on recent discussions with some business stakeholders, certain taxation legislative changes will become effective immediately upon the scheduled conclusion of the project.
What should the project manager do?
Question: 3
The product owner notifies the project manager about a risk that has been identified. What should the project manager do?
Question: 4
A project team member delivered one of the main deliverables on time. During a meeting with the customer, that deliverable does not pass the validation procedure What should the project manager have done''
Question: 5
A project team is developing an engineering system and submitted the first deliverable to the client. The client found that the first deliverable works and corresponds to the design document. However the client thinks that an additional feature can improve the performance of the system, and does not want to accept the deliverable without the additional feature implemented.
What is the project manager's next step?