Question: 1
Based on the input of a senior team member, a corrective action is implemented to address a design issue. After implementation, the team discovers that the corrective action fails to improve design quality.
What should the project manager have done to prevent this?
Question: 2
A car manufacturing company wants to develop an unmanned car as a new product. A project manager was assigned. The company has developed high-level specifications, but the detailed specifications are not clear
How should the project manager develop the work breakdown structure (WBS)?
Question: 3
A project requires specialized technical expertise from the engineering department. However, the senior engineer is leading a team on a separate project, and the only available resource is an entry-level engineer. The senior engineer is highly regarded by the customer and preferred by the project manager.
What should the project manager do first to obtain the senior engineer's participation in this project?
Question: 4
During a monthly executive steering committee meeting, a functional manager states that they have not been made aware of the schedule delays documented in the last status report. What should the project manager do to avoid this situation in the future?
Question: 5
The client is pushing the development team for an urgent software patch to address a bug The team completed the patch, but the tester was unable to sign off on it due to illness. Regardless, the product manager is determined to release the software immediately
What steps should the project manager take?