Cost aggregation is typically performed by aggregating work packages in accordance with the:
Answer : D
Which of the following are outputs of the Monitor and Control Project Work process?
Answer : A
Which schedule development technique modifies the project schedule to account for limited resources?
Answer : C
Which is a tool used in monitoring and controlling project work?
Answer : B
As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?