Question: 1
A project manager identifies a new project task that will not affect the delivery date. What should the project manager do next?
Question: 2
A project must be simultaneously implemented in two countries with a time-zone difference of 11 hours. The
project manager must determine a mutually convenient time to provide stakeholders with information on the
project's schedule, cost, and performance progress.
What should the project manager use to determine this?
Question: 3
A project is dependent upon business owners providing resources to perform an important task Since budget owners may potentially object to this requirement
What should the project manager do next?
Question: 4
As a project progresses the project manager notices that weekly project status meetings are no longer serving the purpose for which they were intended What should the project manager do to improve the meetings?
Question: 5
While preparing a projects third progress report, the project manager identifies that the project will experience delays due to late material deliveries The two previous project reports indicated that the project was on track
What should the project manager do next?