Question: 1
During a project meeting, a team member reports using an innovative method to work on a requirement After reviewing the change log the project manager realizes that the team member added more functionality.
What does this describe?
Question: 2
During project execution, several concerned stakeholders confront the project manager with concerns The project manager discovers that these stakeholders' expectation^ were unrecorded and hence unmet
What should the project manager have consulted to avoid this?
Question: 3
Midway through a project, a subcontractor is replaced. The project sponsor asks the project manager to confirm that the new subcontractor's deliverables meet the client's technical specifications
What should the project manager do to confirm this?
Question: 4
During the project initiation phase, the project manager is identifying key deliverables based on me projects business requirements. 000000000000.The number of key deliverables.
What tool or technique should the project manager use to prioritize the key deliverables?
Question: 5
During a project review, the construction manager reports that the concrete production rate has change over the last three months. What analysis should be conducted?