Free Practice Mock Questions Set 161-165 (Quiz # 33) for PMI PMP Exam, according to official PMI Project Management Professional (2024) exam syllabus topic # 3
Which of the following tools or techniques is used for Estimate Activity Duration?
Answer : D
Which type of analysis is used to develop the communications management plan?
Answer : C
Which of the following is a tool and technique for activity duration estimating?
Answer : A
What defines the portion of work included in a contract for items being purchased or acquired?
Which of the following are inputs to Activity Definition?