Question: 1
During a project review meeting, stakeholders disagree on the project deliverables outlined in the acceptance criteri
a. According to one stakeholder, the project fails to deliver what they understood the acceptance criteria stated it would deliver.
What should the project manager have done to ensure that all project stakeholders understood the acceptance criteria?
Question: 2
After completing a project schedule, the project manager learns that the sponsor wants an earlier completion date without incurring additional costs. What technique can the project manager use to meet these requirements?
Question: 3
A project manager is in the process of developing the cost management plan on a new project which is based on the approved project charter's information. This is an innovative project and the company has not delivered a similar project in the past.
What should the project manager do next?
Question: 4
Six weeks into project execution, a key stakeholder requests a change The stakeholder states that this request should be treated as high priority.
What should the project manager do next?
Question: 5
A government-initiative project has a strict deadline for completion. A kick-off meeting is a requirement, but one critical stakeholder is unavailable to attend Postponing this meeting will delay the project
What should the project manager do?