Question: 1
An international project team consists of local and overseas team members. The local team is responsible for integrating the project's work outputs. During the first integration phase, the need for a pre-validation of work outputs is identified, which will impact the project's cost and schedule.
What should the project manager do next?
Question: 2
During a project's planning phase, a functional manager becomes anxious about the impact of the project on team morale and constantly reaches out the project manager with these concerns.
Question: 3
A project manager performs an audit of a subcontracted supplier to determine if scope, quality, and time requirements are being met. What process is the project manager using.
Question: 4
A vendor provides notices of a delay in the delivery of a key component that is required to complete a critical activity. The project has a schedule performance (SP) of 0.95.
What should the project manager do first?
Question: 5
The project manager of a large software implementation project is preparing for a kick-off meeting. While reviewing all available project information, the project information, the project manager discovers that the project's key deliverables are not clearly identified.
What should the project manager do?