Question: 1
A project is on schedule, and deliverables are being provided on lime During a customer meeting, the client team complains that deliverables fail to meet agreed-upon expectations which is validated by the project team
What should the project manager do to prevent this in the future?
Question: 2
A project management plan is being developed, and the cost development figures are being established On what should the project manager primarily focus during this planning phase?
Question: 3
A proved is delivered that meets the approved business requirements. However, the client identifies a few unrelated issues that will cause a delay in final product approval and impact project closure
What should the project manager do?
Question: 4
During project execution, the marketing manager stales that they do not know the timeframe for the product launch A review of the communications management plan shows that the marketing department was not included as a concerned parry
What should the project manager have done to prevent this?
Question: 5
During an ongoing project, the customer requests that new requirements be delivered without changing the schedule. What should the proved manager do next?