Question: 1
A protect manager has just completed a stakeholder engagement meeting where many points for discussion were deferred The project manager must provide a response to the stakeholders at next month's meeting
What should the project manager do next?
Question: 2
During user acceptance testing, key stakeholders express their dissatisfaction with the new features After investigating the issue if the determined that requirements were not approval requirements were not approved. What should the project manager have created to prevent this issue?
Question: 3
A development project's earned value is US$640,000. and the planned value is US$800,000 What should the project manager do to control this variance?
Question: 4
A medium-sized protect has a high-level timeline at project initiation When reviewing the project schedule the project manager realizes that the timeline may be unrealistic based on the defined scope In addition it is identified that several tasks in the schedule require more time, both before and after to accommodate external task dependencies
What should the project manager do to mitigate the risk of an unrealistic project plan?
Question: 5
Government regulations require that project deliverables be tested and approved by stakeholders before they can be accepted However, these stakeholders are frequently too busy to perform the acceptance tests Without these tests, project quality standards will be unmet, and the project cannot complete its deliverables
What should the project manager do?