Question: 1
You are a project manager working on a software development project. During a project meeting, one of the team members suggests a nice feature that the customer may like. The project manager says yes to this new feature, indicating the project should exceed the customer expectations. This is an example of:
Question: 2
As a project manager of a construction project, in the middle of the project, you are informed by the project sponsor that the project will be terminated because of an inadequate credit limit with the bank. What could have been done differently to prevent this situation?
Question: 3
You are managing a highly complex drug manufacturing project. During the execution of a project, two of the project's stakeholders have just asked for changes that each says should be the number one priority. As a Project Manager, what should you do next?
Question: 4
A project manager is encountering numerous problems on his project. He wants to identify the root causes of the problems, so that he can focus his attention on those causes. Which of the following tools should he use?
Question: 5
Which of the following is a tool or technique used in the create WBS process?