Question: 1
Who is responsible for reviewing change requests and approving or rejecting the change requests?
Question: 2
Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?
Question: 3
Activities on the critical path have which type of float?
Question: 4
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days. What should be your concern?
Question: 5
The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?