A project manager has just started planning his project. If he would like to base his project duration estimate on historical data with a degree of confidence on the accuracy of the estimates, which duration estimation technique would he use?
Answer : A
A project manager is performing a set of processes in the Initiating phase. He is developing a document that formally authorizes the existence of a project and provides the project manager with authority to apply organizational resources to project activities. Which of the following documents contains this information?
You are a project manager, and you are reviewing the deliverables developed by the seller organization. If you would like to review the quality specifications, quantity desired, and quality levels of the deliverable, which document can help you in this scenario?
Answer : B
Which conflict resolution technique is most likely to result in a permanent resolution?
You are working as a project manager in a construction project. During the implementation phase, one of your project team members tells you that a hurricane is likely to happen and will affect the equipment in your project. Asa project manager, which of the following documents should you review FIRST?
Answer : D