Question: 1
Resource constraints on a high priority project may cause schedule delays. The project manager updates the status report sent to stakeholders but few read it. While most stakeholders consider quality as paramount, the engineer believes that the most urgent issue is the schedule. When the delay becomes a reality, the engineer is surprised and angry.
What should the project manager have done to keep the engineer engaged?
Question: 2
A protect manager must quickly transition another project to begin their next assignment. Several issues were scheduled to be fixed the other project's warranty period. but stakeholders are unwilling to accept project deliverables until all issues are completed.
What should the project manager do?
Question: 3
An engineering is commissioning a new mine in a region with territorial disputes. If the mine is not commissioned or time, the project management company may incur enormous fines and reputational damage. The project manage, completes a risk analysis and choose to purchase insurance to cover the fines if the project experiences delays.
What type at risk response did the project manager use?
Question: 4
During protect execution, a high-performing team member leaves Following this loss, a planned quality audit is conducted that indicates work products' quality standards are unmet
What should the project manager do next?
Question: 5
A new project manager takes over a completed project where all deliverables were accepted by the customer. The customer is unhappy that the project was over budget and of poor quality.
What should the project manager conduct?