Question: 1
A project is in the closure phase. The deliverables have been approved by the project sponsor. However the team that will support the delivered product is complaining about a lack of documentation.
What should the project manager have done to prevent this scenario?
Question: 2
During an audit, a team member complains about the quality of the product being produced However, no metnc related to this complaint was taken into account in the quality management plan.
What should the project manager do?
Question: 3
A project manager is unable to explain why several Scrum team members have been unhappy with the team's performance for the past year What would have assisted in identifying these issues?
Question: 4
The project manager has calculated the schedule performance index (SPI) as 1 and cost performance index (CPI) as 1.2.
What is the status of the project?
Question: 5
After a project is completed, the project manager is informed that mistakes made by the team were due to the functional manager not allocating experienced resources What should the project manager do with this information?