Question: 1
Since the client was on leave, a project manager handed over the deliverables of a successfully completed project to the client's project manager One month later, the accounts team informs the project manager that client approval was rejected and invoices are unpaid.
What should the project manager have done to avoid this?
Question: 2
A project manager publishes a survey to assess stakeholder satisfaction on the progress of the project Very few responses to the survey were received in the time provided What should the project manager do to get more input?
Question: 3
An audit was conducted on a project during close out The issue log could not be located in the project management information system (PMIS) What should the project manager do to prevent this from becoming a nonconformance?
Question: 4
A project manager is managing a project that is close to its completion date. The project manager finds that the speed for resolving issues is above average, but critical issues are accumulating and may impact the closing date of the project.
What should the project manager do first?
Question: 5
During a construction project, concrete is unable to be used because heavy rain affected its consistency. This possibility and its estimated costs were already identified in the risk register.
How should the project manager fund the additional costs?