Question: 1
The customer would like to alter the product specifications during the development process following user experience testing Product development will be done with an agile team How can the quality of the product be ensured?
Question: 2
A company has been awarded a project to develop products for a manufacturing company When the project is transitioning to the execution phase, the project manager realizes that no quality requirements have been set for the project
What should the project manager do?
Question: 3
The stakeholders on a new compliance project request a delivery date for the project from the project manager There are a number of internal as well as external dependencies for the project and milestones that have to be met within certain timeframes
What should the project manager do to determine the delivery date?
Question: 4
A customer asks the project manager to deliver a project in 60 days that was previously scheduled (or delivery in 90 days No activities can be performed in parallel The requested change is approved by the change control board (CCB)
What should the project manager do to fulfill this request?
Question: 5
The results of a quality audit show that project team members have not been completing the design reviews required by the quality management plan. The team members have started building several components without reviewing their designs.
What should the project manager do first?