Question: 1
A project manager is leading a new project that involves cross-functional requirements and changes Some key stakeholders are resisting the changes.
What should the project manager do?
Question: 2
During project planning, the project manager wants to transfer as many cost overrun risks as possible to the supplier What type of contract should the project manager use'?
Question: 3
During a project the project manager realizes that a special resource is needed to complete a critical deliverable. The company does not have a resource available with this expertise, and the project manager has already tried to complete the deliverable without the help of a special resource. The project is now behind schedule, and the cost has increased.
What should the project manager have done to avoid this situation?
Question: 4
A project manager has identified two stakeholders across different business divisions in the company whose engagement and full support are needed for a project. What should the project manager be aware of prior to engaging them?
Question: 5
A project manager needs stakeholder approval of the project plans in order to establish an execution baseline. What should the project manager do?