Question: 1
Company A is expanding their manufacturing units to various locations in country A. As this is the first time the company is expanding into this geographic region, the project manager and the team have identified many initial high-level risks.
What should the project manager do throughout the project to manage these risks?
Question: 2
During project implementation, a project manager discovers that the quality of a deliverable does not meet the acceptance criteria. What should the project manager do next?
Question: 3
Six months into a project the first project milestone is due However the project manager finds out that one of the team members has submitted low-quality work that requires rework What should the project manager do next'
Question: 4
During the last few days of an open request for proposal (RFP), there are still many unanswered questions from vendors. The timely award of the contract is on the project's critical path. The project manager is concerned that the award of contract will be delayed.
What immediate action should the project manager take?
Question: 5
While developing a project's benefits management plan, a project manager receives input from some stakeholders that the project has very little value for the company. What should the project manager do next?