Question: 1
A project manager is managing an infrastructure project when a key stakeholder asks for the inclusion of an unexpected requirement. Which project document should the project manager update first?
Question: 2
During the initiation phase of a healthcare IT project the project manager analyzes the project's key benefits based on input from stakeholders and finds that they are inconsistent What should the project manager do first?
Question: 3
A project manager was informed by a stakeholder that the project charter draft submitted for approval contains fundamental errors and inconsistencies. What should the project manager do?
Question: 4
After a risk review, the project manager notes an increase in impact for one of the financial risks. What should the project manager do next?
Question: 5
A project manager has just been assigned to a new project. A similar project is under deployment in another office and is encountering many issues that have led to major delays What should the project manager do next?