Question: 1
A project is in the execution phase, and so far project status reports have indicated that the project is tracking well against its timeframes. The project manager then receives a call from the supplier advising that they're unable to meet the upcoming milestone date because a key team member is ill.
What should the project manager do?
Question: 2
A low-priority and low-risk change request has been planned for almost six months. It is almost the end of the project What should the project manager do?
Question: 3
A project manager is working on a product-line project with a specific deadline. During execution the customer realizes that some extra requirements need to be added and informs the project manager.
What should the project manager do next after receiving the customer's request?
Question: 4
An experienced project manager is building the base cost management plan of a project During this process, the project manager is struggling to receive input from a couple of the stakeholders. The issue has been escalated to the sponsor but input has still not been received.
What should the project manager do to complete the cost estimate?
Question: 5
During the execution phase of a project a new functional manager joins the company to replace the former functional manager During a monthly meeting, the new functional manager expresses confusion about the data provided in the meeting and asks for weekly reports via email because this project affects their department's work significantly After checking, the project manager finds out that the former functional manager did not receive the weekly email report.
What is the cause of this problem?