Question: 1
Due to recent organizational changes, a number of project stakeholders are no longer with the company. What should the project manager do?
Question: 2
A project manager is working in a hybrid environment using both waterfall and agile frameworks This causes some confusion about who does what throughout the project What can the project manager do to help clear the confusion?
Question: 3
One of the team members has been reporting their activities exclusively to their functional manager, instead of following the established procedure of activity reporting within the project management information system (PMIS). What should the project manager do?
Question: 4
After numerous meetings, the project manager was unable to obtain approval of the project management plan because the client needed to check with their superiors. What should the project manager have done to avoid this?
Question: 5
A division manager wants to transfer a key team member off of the project. This may impact the project delivery schedule listed in the contract What should the project manager do in this situation?