Question: 1
A project manager is preparing a project management plan for a transition project for a service in an IT company that resides in different countries. What should the project manager do first?
Question: 2
A project is in its execution phase and many change requests are being implemented. One change request activated new equipment to replace obsolete equipment. Although no longer in use, the obsolete equipment was not disposed of or switched off properly, generating maintenance costs and energy consumption that serve no purpose.
What did the change executor fail to observe?
Question: 3
A project manager is working on a project to create a new software system. In recent sprints, there has been a significant increase in the number of defects. The project team is questioning whether or not the testing being performed is still valid.
What should the project manager do next?
Question: 4
Company A hires a new project manager to join an existing project. The new project manager creates the risk register The risk owner for one risk is someone outside the project team. The risk is now being triggered
What should the project manager do?
Question: 5
Product testing is nearly complete when the project manager overhears a stakeholder mention that the company is likely to rebrand itself This would result in product redesign. After contacting the marketing manager to validate this, the project manager learns that a decision has not yet been made.
What should the project manager do?