Question: 1
A project manager is working on a project that will result in a product that will be used in multiple countries. After the team starts the implementation phase, they detect that the product they are building will need a technology that is not available in one of the countries. When the project manager checks the risk register they notice that this risk was already identified, but no action was taken
What should the project manager have done to avoid this problem?
Question: 2
A project manager is leading project teams across various countries and time zones. When developing the stakeholder engagement plan, the project manager must consider that several stakeholders have conflicting views regarding scope, timeline, and project quality.
What should the project manager do first?
Question: 3
During a project meeting, the sponsor, who is financing the project, asked for the risk status. After being provided with the risk register the sponsor wants to assess the overall risk of the project in terms of possible cost overruns throughout its life cycle
What should the project manager do?
Question: 4
Two members of a project team have differences in opinion on how they complete a task. The conflict is not yet escalated to the project manager and there is no impact to the project. What should the project manager do?
Question: 5
A project manager has a team of diverse professionals with different backgrounds. During project execution, the project manager notices that one team member is struggling with completing tasks on time and meeting quality expectations.
What should the project manager do to address this issue?