Question: 1
A project's cost performance index (CPI) is 1.05 and its schedule performance index (SPI) is 0.9. Based on the information, what is the result of the project?
Question: 2
After completing the project charter, the project manager sends it to the project stakenarios. What should the project manager do before starting the project planning process?
Question: 3
A start-up company's project team completes its first product development initiative, what should the project manager do next?
Question: 4
After stakeholders in a company's sales department examined all the deliverables, they state that mere has been a change in the company strategy. Therefore, important changes must be made to the requirements. The project manager believes that these changes make the deliverables unusable.
What should the project manager do?
Question: 5
A project's most recent status report indicates a schedule performance index (SPI) of 1.1 and a cost performance index (CPI) of 1.2. A key stakeholder then suggests a change to include a value-added feature that would not impact project schedule and cost.
What should the project manager do next?