Question: 1
Because a project is behind schedule, the sponsor suggests reducing the time for quality assurance testing.
What should the project manager do?
Question: 2
A project manager in a weak matrix organization notices that a resource is behind schedule on a project task.
The project manager discovers that this resource was assigned to two other projects by the line manager.
What should the project manager do?
Question: 3
A project manager is assigned to an ongoing project and receives notification from another department that
they were not made aware of timeline slippage on one of the key deliverables. To which document should the
project manager first refer?
Question: 4
While examining the network diagram, a project manager finds resources that are overallocated to non-critical-path task. What should the project manager do to fix this situation?
Question: 5
A project manager receives an approved change request related to a project's governance framework. What
should the project manager do to implement this change?