Question: 1
An issue arises on a project A team member recalls that this issue has occurred before, but cannot remember the solution. Where is the first place the project manager should look to find the solution?
Question: 2
A project team member decides that engaging the customer on some alternative designs is unnecessary if all functionalities are delivered The entire team decides to only engage the technical department on the best product design After user acceptance testing, the customer complains about the selected design
To ensure that the customer accepts the project deliverables what should the project manager do?
Question: 3
A company's organizational culture is open engaging and values continuous improvements Individual employees freely express themselves during meetings on processes policies, and procedures. The project manager wants to respect the organization's values of continuous improvement during the project
Where should the project manager capture lessons learned?
Question: 4
Due to a recent incident, a dissatisfied stakeholder files a complaint about a project that has been closed. What can the project manager do to help resolve this?
Question: 5
To begin transitioning the final deliverables to the client, a project manager develops the project closure documentation. What should be used to develop the project closure documentation?