Question: 1
During a product's testing phase, the customer discovers that a previously identified defect remains unfixed. What should the project manager do?
Question: 2
A project manager is developing a project risk register. What tool or technique should the project manager use to generate a list of all possible project risks?
Question: 3
A manufacturing plant project is ready for hand-over to the maintenance manager. The maintenance manager advises that the new plant is noncompliant with the company's maintenance standards.
What should the project manager have done to avoid this?
Question: 4
Provisional training is provided for a project that is in the process of client hand-over. The client then asks for a step-by-step manual which was not included in the project's deliverables What should the project manager do?
Question: 5
A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?