Question: 1
A project manager notices that work started by the project team is misaligned with an industry regulation. The project manager recalls that this topic was previously discussed during a stakeholder a stakeholder meeting.
What should the project manager review?
Question: 2
The Change control board (CCB) authorizes two corrective actions for implementation. The first action will cause a delay delivering the regular stakeholder communication report. The second action will require mote man hours on a severely delayed task on a critical path.
What should the project manager do first?
Question: 3
During a software development project one team member fails to complete assigned tasks which prevents integration with other components and causes a milestone to be missed. The team member did not inform the project manager about any problems with their tasks.
What should the project manager do first to communicate this to the sponsor?
Question: 4
A project manager completes the requirements traceability matrix but indicates that not all requirements will be addressed. What should the project manager do to resolve this situation?
Question: 5
A new smart phone is introduced Market research indicates that customer expectations for the browsing speed of certain applications are unmet. To mitigate this, the quality team reviews the design and decides to reproduce the product.
What is this cost of rework called?