Question: 1
A project manager begins the estimating process for a new project. Since the project manager knows that a similar project was completed 18 months ago, what type of estimating should they use?
Question: 2
Four months into a one project, the customer requests a change. The change control board (CCB) reviews and approves the change, but one stakeholder believes it is out of scope.
What can the project manager reference to show that the change request was appropriate?
Question: 3
Members of a project learn are based in two countries Experienced resources work together at company headquarters in country A, while the remaining resources who deliver the project work, are located in the client's office in country B. The project manager is located in the client's office most of the time Last month, the experienced resources discovered several unacceptable issues, and expressed concern that the project manager is unable to fairly evaluate all efforts This causes the experienced resources' productivity and morale to decline
What should the project manager do?
Question: 4
In a multi-site development project, sharing documents within the project team is identified as a security risk Introducing a new software release would mitigate this risk. What should the project manager do first?
Question: 5
To implement a customer relationship management (CRM) software solution, a systems project manager must identity the required human resources. What should the project manager reference?