Question: 1
During a project's execution phase, a new stakeholder is identified who is critical to the project's success. What should the project manager do next?
Question: 2
A project has live finish-to-start (FS) activities
* Activity A takes one day.
* Activity B follows A and takes five days
* Activity C follows B and takes two days.
* Activity D follows B and A and takes two days.
* Activity E is preceded by C and D and takes two days
What would be the critical path(s)?
Question: 3
Due to commitments to another project, an accountant fails to deliver an important report, what should the project manager nave referenced to avoid this?
Question: 4
A new project manager joins a company to work on a new. first-of-its-kind initiative. How can the project manager ensure that the project value proposition is aligned with the company's strategic objectives?
Question: 5
While preparing for project hand-over to the operations team, the project manager discover that an audit report from an early project phase is missing. What should the project manager do?