Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
A major project deliverable is completed. What should the project manager and team do to conform that specifications have been met?
Question: 3
A team needs to install a large piece of equipment for a project, which can only be done when the plant is shut down Plant shutdown is planned every year during the second week of May Earlier in the project, the project manager identified a corresponding risk ot project delay due to missing an installation window At the end of April, an accident occurs that causes the plant to have an unplanned shutdown. The project team reschedules and completes the installation of the major equipment during this time.
What should the project manager do next?
Question: 4
Which of the following inputs is required for the WBS creation?
Question: 5
You are participating in developing the project charter for a new project assigned to you. Which of the following is input to develop the project charter?