Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
While managing a project for a multinational company, a project manager continues to accept changes from the client to maintain a good relationship and secure new business. Three quarters of the way through the project, the budget is depleted.
What should the project manager have developed to prevent this?
Question: 3
A project successfully met its goals on time and all deliverables were completed and delivered. The project team needs to be disassembled so team members can go back to their functional jobs.
What should the project manager do in order to proceed with project closure?
Question: 4
An organization's objectives require the reduction of costs associated with future failures What should the project manager do when budgeting cost?
Question: 5
Two issues remain in the quality issue log The first is within acceptable threshold limits, and the corrective action will be fast increase customer satisfaction and reduce long-term external repair costs The second is outside performance baseline limits and will impact the project schedule
What should the project manager do?