Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
A team member is working the required hours, but is delivering inadequate output. What should the project manager do first?
Question: 3
Your most recent project status report contains the following information: EV = 3,000, AC = 4,000, and PV = 5,000. The schedule variance is:
Question: 4
A project team completed all development activities and delivered the product to the customer. The project manager immediately released the team to begin work on a new product. One month later, the customer complains that many functionalities fail to work as expected
What should the project manager have done to avoid this?
Question: 5
A recent project took 12 months to complete however a new similar project is estimated to the first project?