Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
A project to implement a new business improvement is initiated by the sponsor. The project manager has concerns regarding high-level requirements.
What should the project manager do?
Question: 3
A project has five activities: A-B-C-D-E. All are finish-to-start (FS). Activity duration and order of implementation are as follows:
Activity A has a duration of one day. Activity B follows A and takes five days Activity C follows B and takes two days. Activity D follows B and A and takes two days. Activity E is preceded by C and D and takes two days.
What are the total float and free float days for activity D?
Question: 4
Which of the following is an example of push communication?
Question: 5
A project manager arranges quality management training for the entire project team The training will relate to the project's final product deliverable
In what cost of quality (COQ) category should the project manager classify this training?