Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
While meeting with the project team, the project manager learns that the new department manager, while abroad is raising questions. What should the project manager do next?
Question: 3
A project is being audited to ensure compliance with organizational policies. What process is being conducted
Question: 4
Which of the following processes groups accept the project deliverables as an output?
Question: 5
You are managing a design project that would provide design drawings to your customer. The requirements of this project were not clearly defined in the beginning, and there would need to be many changes based on customer feedback as the project evolves. You elaborate the work of the project to the level of detail you know at the time. Which of the following techniques would be the most helpful while defining activities for the project?