Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?
Question: 3
An IT project is approved and a project management plan is in place. What should the project manager do next?
Question: 4
You are a project manager working on a software development project. Your Senior Manager has asked you to begin identifying risks and to use an information gathering technique. Which one of the following risk identification approaches is a data analysis technique?
Question: 5
During a project with a tight timeframe the project manager needs continuous stakeholder buy-m and input to avoid errors Inevitably changes occur as the project progresses
What should the project manager do?