Question: 1
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Question: 2
Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?
Question: 3
A project manager has been receiving enhancements to a product that will be launched in five months. What should the project manager do next to ensure that these enhancements are included in the product release?
Question: 4
To increase the likelihood of project success, project manager A interviews project manager 0, who completed a similar project. However, project manager B is unable to recall the details
What should project manager A do now to obtain this information?
Question: 5
You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and you have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?