Question: 1
At the start of a project. the project sponsor sends an email to the entire project team. The email contains expectations of the implementation outcome that greatly exceed the approved business case and scope defined in the project charter.
Aiming to minimize the adverse impacts of this communication, what should the project manager do first?
Question: 2
A project manager Is working on a multiphase networking project. Phase 1 is scheduled to finish next month. Phase 2 Is in the initiation phase and the budget approval is past due. However, the project manager has a strategy in place for approval.
What should the project manager use to monitor this and help ensure a delay does not impact project performance?
Question: 3
A project manager realizes that there is an inconsistency in the project requirements. The team is unable to continue without clarification.
What should the project manager do?
Question: 4
A complex project is divided into phases. The project manager is closing a minor phase when the project team realizes that one deliverable was not accepted by the audit department. The audit department was mistakenly not notified during this phase, but complained about the deliverable during the closure meeting.
What should the project manager do?
Question: 5
A project manager joins an ongoing firm fixed price (FFP) project. The project manager discovers that there is no lessons learned repository and that, to date, no retrospective meetings were held. The existing project budget does not cover lessons learned activities and, so far, this has not created any issues.
What should the project manager do?