Question: 1
A project manager developed a project management plan for a team composed of members based in three countries. The project manager assumed a 40-hour work week for all team members. However, during project execution, the project manager learns that one country's team members work a 35-hour week.
Where should this information have been captured?
Question: 2
A project manager is beginning a new project where the sponsor and main stakeholders have a specific protocol and confidentiality requirements. Some of these stakeholders have not collaborated with each other or with this project's domain previously.
Which data-gathering technique should the project manager primarily use to define the requirements?
Question: 3
A project is behind schedule due to an incorrectly estimated task on the critical path. What should the project manager do?
Question: 4
During a weekly status meeting, a team member informs the project manager that the design submitted to the local government for approval has been rejected due to an error in the blueprint Resubmission of the design will require an additional two weeks.
What should the project manager do first?
Question: 5
Provisional training is provided for a project that is in the process of client hand- over. The client then asks for a step-by-step manual, which was not included in the project's deliverables
What should the project manager do?