Question: 1
A project's most recent status report indicates a schedule performance index (SPI) of 1.1 and a cost performance index (CPI) of 1.2 A key stakeholder then suggests a change to include a value-added feature that would not impact project schedule and cost.
What should the project manager do next?
Question: 2
A retail company engages a new service provider to implement a replenishment system for its stores. The current system is built on old technology, fails to cater to new business processes, and performs slowly. User acceptance testing shows that the new system accommodates all business processes, but is slower than the original.
The use of what tool or technique would have avoided this problem?
Question: 3
While developing the project charter stakeholders disagree about the project's most important objectives. What should the project manager do to resolve this?
Question: 4
One year into a five-year project, the project manager realizes that the reason for high team turnover is that the team does not receive the same financial allowances as other teams that are working on the same project The project manager forecasts that with this high staff turnover rate, the project will suffer a two-and-a-half-year delay. The amount to cover additional disbursements was not included in the contract, and the project sponsor is unwilling to renegotiate.
What should the project manager do?
Question: 5
A project manager is managing a two-year agile project with monthly iterations The project manager identifies the following risk during project initiation: "Rapid development of new technologies used by the industries and stakeholders may reduce the delivered value."
Which approach can the project manager use to mitigate the stated risk?