Question: 1
During e protect, a business need changes and the project is canceled. The project manager meets with prefect team members to collect information learned during the project Where should this information be documented?
Question: 2
A project manager is reviewing an inspection report for a subcontractor. The report shows that the subcontractor is performing behind schedule and will be unable to deliver on time What should the project manager do1?
Question: 3
Before authorizing resource assignments, a company's project management office (PMO) requires that the project manager present the approved project charter However, the project sponsor is on vacation for the next three weeks Stakeholders want the prefect to start as soon as possible
What should the project manager do?
Question: 4
A project has been completed, and the product delivered to the client However, the product has a defect and only partially meets business needs.
Where mil the project manager document an estimate of when the business need will be fully met?
Question: 5
A stakeholder instructs a propel manager 10 transfer a key resource from project A's team to project B's team. What should the project manager do first?