Question: 1
A project team is using agile methodologies 10 develop a complex system. The company does not want to help with any preliminary reviews of product testing because they believe testing is not their responsibility What should the prefect manager do to encourage the company to agree to preliminary reviews or testing?
Question: 2
A software development protect lot a financial institution is underway. On the software solution's deployment date, the software produces incorrect information. What should the project manager have done to avoid this?
Question: 3
A functions manager complains mat an employee is invoked in too many project meetings, wasting valuable time mat could be used for other responsibilities. To what document should the project manager refer to address this?
Question: 4
Project documentation includes a few assumptions considered during the early stages of the protect During the requirements gathering sessions, the project sponsor states that the protect fails to represent their expectations and requests additional functionalities
What should the project manager do next?
Question: 5
A project manager identifies a risk that a product could endanger its users. A risk response has been proposed that will decrease the product RC4 by 10 percent, but the project will still meet financial requirements What should the project manager do?