Question: 1
During the project initiation phase, The project manager is identifying key deliverables based on the project's business requirements. The project manager believes that the timeline is unrealistic due to the high number of key deliverables.
What tool or technique should the project manager use to prioritize the key deliverables?
Question: 2
While reviewing a status report, a project manager notices that, over a period of six months, the coding quality for one developer is statistically lower than another developer assigned the same task. Which tool should the project manager use to trace the problem's back to its action root cause?
Question: 3
A project's cost performance index (CPI) is 0.3. The CFO instructs the project sponsor to restrict the project scope to bridge the CPI back to 1 within the months. While reviewing the approval change requests for removed activities, the project manager becomes concerned about the resulting cost the nonconformance.
What should the project manager do?
Question: 4
A new execute asks the project manager to share sensitive project information that had not been a part of communications with the previous executive. What should the project manager do?
Question: 5
An approved change request will require the modification of associated documents, deliveries, and the project baseline. What documents should the project manager update?