Question: 1
As a project manager, you are ensuring that the quality management process is followed on your project. However, failure to meet the quality requirements can have serious negative consequences for any or all of the project's stakeholders. During a project update meeting, one of the key stakeholders expressed his displeasure over the project management approach. One of the produced deliverables had major defects which required a rework. Defects in the produced deliverables cause rework which costs the company $ 2000.This rework has increased costs, and you're beginning to notice some signs of poor morale because of the rework. Which of the following statements is true?
Question: 2
A change has occurred in your project. You've documented the change, filled out a change request, and submitted that request to the change control board (CCB). However, the change request has been rejected by the change control board. What's the NEXT thing that must happen on the project?
Question: 3
A. You should not document the new feature.
Question: 4
You are a project manager tasked with a project of constructing six similar buildings in sequence. The project is estimated to cost $250,000 with a project timeline of four months. During a review after two months, you found that only two buildings are ready. The Actual Cost is $100,000. The project status is:
Question: 5
After your last status meeting, your customer has come to you with a complaint in one of the deliverables that will cause the final product to be delayed. You look at his complaint and feel that it's not justifiable and that the product really does meet its requirements. What's the first thing that you do?