Question: 1
You project is running with a CPI of 1.1. The EAC is $100,000. What is the BAC?
Question: 2
You are a project manager, and you want to perform some analysis of defects and problems that have been discovered in the project. Which chart can reveal factors that might be linked to potential problems within your project?
Question: 3
You are assigned as the project manager on a new project, and you want to follow the best practices from the very beginning of the project. You understand the importance of having a formal kick-off meeting to launch the project with all your key stakeholders, including the customer, the project sponsor, selected project team members and selected stakeholders. However, there have been too many sidebar conversations and arguments. As a project manager, what could have been done to avoid such a situation in the kick-off meeting?
Question: 4
Which of the following processes groups accept the project deliverables as an output?
Question: 5
You work as a project manager for your company. You have completed the risk identification process for your project. Which of the following is an output of the Identify Risks Process?