Question: 1
Based on the following table, what are the total float and free float for activity (H)?
Question: 2
An asphalt company is demanding a code change to a software module your team is implementing to generate Safety Data Sheets for them. The change will add only one week to the critical path. As the project manager, what is your next step?
Question: 3
Your project is due for a financial review and you have gathered some data. Your EV is $690, your AC is $720 and your BAC is $900. What is your EAC?
Question: 4
After a major milestone release, one of the key stakeholders are not happy and complain their requirements are not being met. In which of the following processes should the project manager have involved them to ensure their acceptance of the project deliverables?
Question: 5
Who is the person responsible for making changes in the Project Charte?