Question: 1
The total budget for a 12-month project is $100,000. You have completed three months' worth of work and are in the 4th month of your project. The total amount spent till now is $35,000. What is the project status?
Question: 2
Which of the following stakeholder analysis techniques are recommended when you need to analyze project stakeholders based on assessments of their level of authority or ability to influence the outcomes of the project?
Question: 3
In your project, if earned value (EV) is larger than planned value (PV)
Question: 4
You have just joined a new organization as a project manager. The project is currently in the executing phase. You then realize that no stakeholder register exists for the project. Since you are new to the organization, you want to ensure that you use its templates for documents. Therefore, your search for a template for a stakeholder register in the:
Question: 5
If your project is under budget, your cost variance (CV) is: