Question: 1
An experienced project manager with a technical background has been assigned to a complex project While in the planning phase, the project manager conducted the cost estimation for the project based on their experience using the work breakdown structure (WBS) estimation technique Unfortunately, the project exceeded the estimated budget and failed to be delivered.
What should the project manager have done to prevent this?
Question: 2
A project manager is working on a request for proposal (RFP) to be sent out Which information or artifact should be used in the supplier/vendor selection criteria?
Question: 3
A data center facility was built near a resident community. The data center was backed up with a generator to maintain uninterrupted power supply. A few months after project completion, the city's municipal office receives complains from residents about generator noise. Upon inspection, it is evident that the installed generator causes more noise than was specified in the municipality standards.
What should the project manager have done to avoid this issue?
Question: 4
A project manager is in the process of developing the project budget and has reservations about the accuracy of the quotes being received from a number of contractors. The deadline for getting the budget approved is only a few days away.
What can be done in a relatively short amount of time to increase the likelihood of staying within the project budget?
Question: 5
A complex system is being replaced and detailed requirements have just been completed While the project is just beginning the execution phase the project manager receives a call from a key stakeholder on a critical function that must be added. The stakeholder assures the project manager that this change does not impact the existing cost or schedule.
What should the project manager do next?