Question: 1
A project manager is tasked with proposing an implementation strategy for a project that will be delivered over a period of five years. What should the project manager do first?
Question: 2
The project team has planned to complete 10 activities in 10 working days. During the seven days, the team members have finished five activities, and they escalate that one activity was underestimated, which requires five additional days to complete.
What should the project manager's next step be?
Question: 3
A project manager receives an email requesting modification to a project's baseline. From whom should the project manager request formal approval to implement this change?
Question: 4
A project has been stopped during the execution phase because the construction methods are not in compliance with environmental regulations. The project manager was not aware of the environmental requirements of the project and now needs advice on how to deal with environmental compliance in future projects.
What should the project manager do to avoid a similar situation in future projects?
Question: 5
A project manager just arrived in a new company department and was appointed to a new project. Management gives the project manager a short briefing and asks the project manager to write the project charter by the end of the week.
What should the project manager do first?