Question: 1
One of the key stakeholders for a project sent an email with the project sponsor copied that raises concerns regarding the progress of the project. Upon investigation, the project manager finds out that the stakeholder had requested a status report from one of the team members and received an outdated report.
What should the project manager do in this situation?
Question: 2
The change control board (CCB) has just approved a change that will cause some rework, and the project team is not in total agreement with the change. What should the project manager do?
Question: 3
While reviewing a project management plan for approval, one of the key stakeholders states that the project needs to be completed three weeks prior to the planned date. How should the project manager address this issue?
Question: 4
A project's core team was reassigned to a partially completed project. The new team underestimated the scope and consistently reported that their tasks were on track. The day before a major deliverable was duer the project manager learned that the product would actually be delivered 10 days behind schedule
What could the project manager have done to avoid this situation?
Question: 5
The project manager of a global franchise is assigned to deliver five stores in five different countries The stores are similar in scope, but the budgets will be managed independently in local currency. The team identifies currency fluctuation as a high-probability risk, which is recorded in the risk register. The team decides that the benefit of a favorable currency fluctuation in one country will be used to offset any unfavorable currency fluctuation in another country to preserve the overall program budget.
What should the project manager do?